Supply and install of 18m Cat Ladder Stadium Masts

Name of Project:

Supply and Installation of 18m Cat Ladder Stadium Masts – University Project, Durban

Description of Project:

Supply and installation of 18 m cat ladder stadium masts for a university sports facility in Durban, KwaZulu-Natal. The project included the supply of the stadium masts, delivery to site, mast installation, and setup to provide reliable lighting for the sports field. The project was completed in 2026.

Project Details

Location:

KwaZulu-Natal – Durban

Industry:

Education

Year of completion:
2026
Scope Requirement:

Global High Mast supplied and installed 18 m cat ladder stadium masts for a university sports facility. The scope included supply of the masts, delivery to site, installation, and ensuring the lighting infrastructure was ready for stadium use.

Challenges:

No challenges were encountered during the project.

Solutions:

No specific solutions were required as the installation proceeded smoothly.

Final Result:

The project was successfully completed with the installation of the stadium masts, enabling the university to host sports matches and training sessions during night-time hours.

Other:

Global High Mast is proud to have contributed to improving sports infrastructure at the university.

 

 

Installation of 20m Solar High Masts

Name of Project:

Installation of 20m Solar High Masts – Rural Project, Limpopo

Description of Project:

Turnkey installation of 20 m solar high masts for a rural facility in Limpopo. The project included foundation works, in-house manufacturing, delivery to site, mast assembly and rigging, installation and testing of lighting, final finishing, and commissioning. The project was completed in 2025.

Project Details

Location:

Limpopo – Rural Area

Industry:

Manufacturing and Installation of Solar High Masts

Year of completion:
2025
Scope Requirement:

Global High Mast delivered a full turnkey solution, managing the project from start to finish. The scope included foundation construction, in-house manufacturing of 20 m solar high masts, delivery to site, mast assembly and rigging, installation and testing of lighting systems, final finishing, and commissioning.

Challenges:

Unfavourable weather conditions during installation resulted in limited working windows on site, particularly affecting lifting and rigging operations.

Solutions:

To ensure deadlines were met without compromising safety or quality, the installation programme was adjusted and the on-site installation period was extended by 2 days, allowing all work to be completed to specification.

Final Result:

The project was successfully completed with a fully operational solar high mast lighting system. All performance and safety requirements were met, and the client was satisfied with the quality of workmanship and service delivered.

Other:

Global High Mast is proud to have been part of this prestige project.

 

 

Installation of 20m Mid-Hinge Masts 

Installation of 20m Mid-Hinge Masts

Name of Project:

20m Mid-Hinge High Mast Installation – Municipal Project, KZN.

Description of Project:

Turnkey installation of 20m mid-hinge high masts for a municipal project in KwaZulu-Natal. The project included foundation works, in-house manufacturing, delivery, mast assembly and rigging, light testing, final finishing and commissioning, completed in 2025.

Project Details

Location:
KZN
Industry:
Manufacturing of High Masts 
Year of completion:
2025
Scope Requirement: 
Global High Mast delivered a full turnkey solution, managing the project from start to finish. The scope included foundation works, in-house manufacturing, delivery to site, mast assembly and rigging, light testing, and final finishing and commissioning.
Challenges: 
Unfavourable weather conditions during installation resulted in limited working windows on site.
Solutions: 
To ensure deadlines were met without compromising quality or safety, the project team extended the on-site installation period by an additional two days, allowing all work to be completed to specification.
Final Result: 
The project was successfully completed with a fully operational high mast system. The client was satisfied and happy with the outcome, and the installation met all performance and safety requirements.