Name of Project:
20m Mid-Hinge High Mast Installation – Municipal Project, KZN.
Description of Project:
Turnkey installation of 20m mid-hinge high masts for a municipal project in KwaZulu-Natal. The project included foundation works, in-house manufacturing, delivery, mast assembly and rigging, light testing, final finishing and commissioning, completed in 2025.
Project Details
| Location: KZN |
| Industry: Manufacturing of High Masts |
| Year of completion: 2025 |
| Scope Requirement: Global High Mast delivered a full turnkey solution, managing the project from start to finish. The scope included foundation works, in-house manufacturing, delivery to site, mast assembly and rigging, light testing, and final finishing and commissioning. |
| Challenges: Unfavourable weather conditions during installation resulted in limited working windows on site. |
| Solutions: To ensure deadlines were met without compromising quality or safety, the project team extended the on-site installation period by an additional two days, allowing all work to be completed to specification. |
| Final Result: The project was successfully completed with a fully operational high mast system. The client was satisfied and happy with the outcome, and the installation met all performance and safety requirements. |